Order confirmation for an electrical contractor: what it must contain, when the contract is formed and what to do when it deviates

An order confirmation is not required, but it fixes what applies: scope, price, date. What it must contain, when the contract is formed and what to watch for when it deviates.


An order confirmation is not required: a contract is formed when both sides want the same thing and say so, expressly or tacitly (Art. 1 CO), and it needs no particular form unless the law prescribes one (Art. 11 para. 1 CO). You write one anyway, because it fixes what applies — scope, price and date — before anyone orders material or books a day. And because in one case it is the confirmation that concludes the contract.

What an order confirmation is

An order confirmation is the contractor's statement to the customer that it accepts the order, with scope, price and date as agreed. It has two faces, and which one applies depends on what came before:

  • The customer has accepted your quote. The contract was formed with that acceptance. Your confirmation repeats what applies and makes it provable. It concludes nothing, it secures.
  • The customer ordered without a quote — on the phone, by e-mail, on site — or on a quote with a reservation. Then the customer's order is the offer and your confirmation is the acceptance. It is the confirmation that concludes the contract.

That is not a technicality: it is the difference between already being bound after a call that ended «yes, we'll do it» and not being bound. Whoever does not write it down argues later about what was ordered.

When the contract is formed — and what not to overlook

Four rules of the Code of Obligations decide this, each with the case in which it turns up in an electrical business:

  1. The acceptance must match the quote. Concluding a contract requires the «mutual and corresponding expression of intent» of the parties (Art. 1 para. 1 CO). If your confirmation changes the price, the scope or the period, it no longer corresponds: it does not agree with the customer, it says something else. For secondary points the law is more lenient. Where the parties have agreed on all essential points, it is presumed that reserving secondary points does not prevent the contract from binding (Art. 2 para. 1 CO); if no agreement is reached on them, the court decides according to the nature of the transaction (Art. 2 para. 2 CO). What is «essential» remains a question of the individual case.
  2. The quote's period binds the customer. If the quote sets a period, you remain bound until it expires and are free again if the acceptance does not reach you before then (Art. 3 CO). If the acceptance was sent in time but arrives late, you must give notice without delay if you do not want to be bound (Art. 5 para. 3 CO). Silence therefore costs something here: whoever does not answer can stay bound.
  3. Silence can be acceptance. Where, because of the particular nature of the transaction or the circumstances, an express acceptance is not to be expected, the contract is deemed concluded if the offer is not rejected within a reasonable time (Art. 6 CO). Whether that applies to a customer's order depends on the case. Do not rely on it: confirm.
  4. The effect starts on dispatch, and a revocation only counts if it arrives first. A contract concluded between parties not present takes effect from the moment the acceptance was dispatched (Art. 10 para. 1 CO). You can withdraw it only if your revocation reaches the customer before or with the acceptance (Art. 9 para. 2 CO). So only send the confirmation once it is correct.

A note on the customer's silence: someone who does not answer your confirmation has not thereby agreed. How the Federal Supreme Court treats confirmation letters in trade was not read for this article. If you change anything against the quote, ask for an express «agreed».

What goes into an order confirmation

The Code of Obligations prescribes no minimum content. What has proved its worth is what prevents disputes:

  1. Reference: number and date of the quote, date and form of the acceptance («by e-mail on 12 November 2026») or, without a quote, the order you are answering.
  2. Customer and property: who orders, where the work takes place, who the contact on site is and how you get in.
  3. Scope and price, as in the quote, or as an attachment. With the price form: fixed, approximate or Regie. How they differ is covered in «Quote variation: fixed price, estimate or Regie».
  4. Date: execution from a date or within a window, and what the customer must provide until then (access, clear walls, power).
  5. Payment terms: Akonto, payment period, Skonto. See the articles «Payment on account (Akonto) for an electrical contractor» and «Skonto (cash discount): meaning, calculation and deduction».
  6. Deviations from the quote, if there are any, in one place and named as such. Hiding them in running text only lets the customer say later that they did not see them.
  7. A sentence on extra work: whatever goes beyond the confirmation is agreed as a variation, before execution.

What does not belong is a second description of the scope: refer to the quote instead of rewriting it. Two versions of the same scope end up contradicting each other.

Example: sub-board in a detached house

Assumed figures. The quote of 9 November 2026 (fixed price CHF 4'800.00 excl. VAT, valid until 7 December 2026) was accepted by e-mail on 12 November.

ItemContent of the confirmation
ReferenceQuote of 9 November 2026, accepted by e-mail on 12 November 2026
PropertyDetached house, contact on site: Ms Example, keys with her
Scopeas the quote, items 1–4, fixed price CHF 4'800.00 excl. VAT
Not includedChasing and painting, disposal of the old board
DateExecution in week 3 (from 18 January 2027), power cut of about 4 hours
PaymentAkonto 30 % = CHF 1'440.00 excl. VAT at the start, balance after acceptance, 30 days net
Deviationnone
Extra workVariation before execution

It fits on one page and takes five minutes to write. In a dispute over «that was never agreed» it is the sheet both sides point at.

Your supplier's confirmation

The word also comes from the other side: when you order material from the wholesaler, your order is the offer and its order confirmation the acceptance. Check it before you file it: quantity, article number, price, delivery date. If it deviates, the supplier has not agreed with you, it has written something else (Art. 1 para. 1 CO), and you decide whether to accept it.

How elektro.box handles the order confirmation

When the customer accepts the quote, by link and signature on the device or by e-mail, the order confirmation goes out by itself. When and to whom the quote went is shown beside it. The page Quote, rapport, invoice shows how quote, confirmation and invoice hang on the same Beleg.

Common questions

Is an order confirmation required? No. A contract is formed by a corresponding expression of intent, express or tacit (Art. 1 CO), and needs no form unless the law prescribes one (Art. 11 para. 1 CO). The confirmation is useful anyway, because it proves the content.

Is the contract formed with the quote or with the order confirmation? If the customer accepted your quote, with the acceptance (Art. 3 CO). If the customer ordered without a quote or on a quote with a reservation, the order is the offer and your confirmation is the acceptance that concludes the contract.

Does the customer have to sign the order confirmation? No, the law does not require it (Art. 11 para. 1 CO). If you changed anything against the quote, ask for an express «agreed»: a deviating statement is not a corresponding one (Art. 1 para. 1 CO).

What if the customer accepts the quote too late? If a period is set and the acceptance arrives after it expires, you are free again (Art. 3 para. 2 CO). If it was sent in time but arrives late, you must give notice without delay if you do not want to be bound (Art. 5 para. 3 CO).

Related articles


Sources: Federal Act on the Amendment of the Swiss Civil Code (Part Five: Code of Obligations, CO, SR 220), Art. 1, 2, 3, 5, 6, 9, 10 and 11, fedlex.admin.ch, version of 1 January 2024, retrieved on 16 November 2026. Not read: the provisions on the contract for work (Art. 363 ff. CO), the SIA 118 standard and Federal Supreme Court case law on the confirmation letter; the article says nothing about them. The figures in the example are assumed, the table's fields are a recommendation and not a statutory list. This article is not legal advice: whether a deviation is «essential» is decided by the court in the individual case.