18 September 2026
Since 1 July 2021, not every installation job has to be reported any more — only what is on the ESTI's list: load increases above 3.7 kVA, grid connections, PV, storage, charging stations, building mains, metering equipment, temporary installations. Who submits the installation notice, who signs it and what happens without one.
An installation notice (Installationsanzeige) must be submitted to the grid operator before work begins if the job is on the list in ESTI Directive 221: new installations and extensions that increase the load by more than 3.7 kVA, dismantling of more than 3.7 kVA, a new or altered grid connection, equipment causing grid interference, power generation systems, energy storage, charging infrastructure for electric vehicles, building mains and the grid operator's metering equipment, and temporary installations. Everything else has not been subject to the reporting duty since 1 July 2021. The duty applies equally to every holder of an installation permit, and the grid operator determines the content and form of the notice.
That is the short version. The long one is worth reading, because the 2021 revision turned the principle on its head — and because two things that look like a notice are not one.
An installation notice is the report of an installation job to the grid operator before the work is carried out — the form in which an electrical contractor fulfils its reporting duty under Art. 23 of the NIV (Low-Voltage Installation Ordinance). The NIV itself does not use the term; it speaks of "reporting duties". The ESTI (Federal Inspectorate for Heavy Current Installations) writes in its Directive 221 that this report is "referred to in practice as the ‹installation notice (IA)›".
Art. 23 para. 1 NIV says who owes it: "Holders of a general installation permit and those of a substitute permit must report installation work, before it is carried out, to the grid operator to whose low-voltage distribution network the electrical installation is connected." Art. 25 para. 1 says the same for holders of limited installation permits. The addressee is always the grid operator whose network the installation is connected to — not the ESTI.
Two things are not an installation notice, although they are often called one:
Until mid-2021 the principle stood without a list; exceptions were governed by an ESTI exemption of 30 November 2018, which Directive 221 repealed. With the revision of Art. 23 and 25 NIV, in force since 1 July 2021, the ESTI has the power "to lay down exceptions to the reporting duty" — and it has laid them down exhaustively in Directive 221. The principle is still in the directive ("all installation work" is to be reported), but section 3 turns it around: a report must be made in the following cases; "in all other cases there is no reporting duty".
The list, verbatim from the directive:
The list applies "to all holders of installation permits" — the general, the substitute and the limited permit alike.
Three items on it are underestimated in practice. Charging infrastructure is on the list with no load threshold: a wallbox must be reported even if it stays below 3.7 kVA — the 3.7 kVA is the threshold for load increases in general, not for the charging station. Energy storage is a separate item on the list, independent of the PV system it belongs to. And temporary installations must be reported even though they disappear again: the construction-site installation is worth a notice, and so is the village fair.
Everything not on the list: replacing a socket, a light fitting, a household appliance; extending a final circuit in a way that increases the load by less than 3.7 kVA; an alteration that touches neither building mains nor metering equipment. Anyone who still sends an installation notice for these today is doing nothing forbidden — they are filling in a form nobody needs.
What does not go away with the reporting duty is the inspection. The initial verification during construction is mandatory for every installation job and must be recorded (Art. 24 para. 1 NIV), reported or not. Only the formal safety certificate may be dispensed with, and only if four criteria are met at the same time: repair or replacement of a low-voltage product, a change in load of no more than 3.7 kVA, no alteration to building mains, consumer lines or distribution lines — and no reporting duty under the list above. The report of the initial verification, handed to the owner, is then sufficient. What that report must contain is covered in the article «Measurement and test report: duty and content».
So the reporting duty and the certification duty are connected, but not in the way one might think: it is not the notice that triggers the safety certificate — rather, its absence is one of four conditions under which the certificate may be dispensed with.
The directive is precise here. For a general installation permit, the report is signed by a qualified person under Art. 8 NIV or by a person authorised to carry out inspections under Art. 27 para. 1 let. a NIV — in both cases one who is named in the installation permit. For a substitute permit, the person named in that permit. For a limited installation permit, the person carrying out the work.
So the electrician doing the job does not sign the notice; nor does the office that fills it in. It is the person named in the permit — and that person must currently be employed by the business, as the ESTI expressly states in its FAQ on the safety certificate.
The NIV does not prescribe the form. Since the reporting duty "serves exclusively the tasks of the grid operators", it is up to them, according to the directive, to specify the desired form — portal, form or email — and also "to determine for themselves" the content of the report. A business working in three grid areas therefore has three notices, and the question "what goes in it" has three answers.
The reporting duty is one of the duties attached to the installation permit, and the NIV makes breaching these duties an offence: Art. 42 let. c lists them "in particular" in seven items, so the enumeration is expressly not exhaustive. The penalty is set out in Art. 55 para. 3 of the Electricity Act (EleA).
In practice, what happens before any penalty matters more. A grid operator that learns of a reportable job only from the safety certificate has not checked the grid connection, has not ordered the meter and has not assessed the grid interference. It may request further information and demand the technical documents (Art. 38 para. 2 NIV), and it may refuse to connect an installation that does not comply with its Werkvorschriften. The business is then left with a finished installation that nobody will approve — and with a customer asking why.
A late notice is therefore better than none. The directive requires the report "in good time before work begins"; if you notice it is missing, submit it late and say so.
Three things the installation notice depends on day to day:
Today the list most often catches the charging station: it must be reported with no load threshold, and depending on the property the consent of the owners' association or the landlord comes on top. How the two fit together is explained in the article «Wallbox in condominium ownership».
Does every electrical installation have to be reported to the grid operator? No, not since 1 July 2021. Only the thirteen cases in section 3 of ESTI Directive 221 must be reported — load increases above 3.7 kVA, grid connection, grid interference, power generation, storage, charging infrastructure, building mains and metering equipment, temporary installations. Everything else is exempt from the reporting duty.
Does a wallbox below 3.7 kVA have to be reported? Yes. "Connection of charging infrastructure for electric vehicles" is on the list with no load threshold. The 3.7 kVA applies to load increases in general, not to the charging station.
Who has to sign the installation notice? For a general installation permit, a qualified person or a person authorised to carry out inspections who is named in the permit; for a substitute permit, the person named there; for a limited permit, the person carrying out the work.
What is the difference between the installation notice and the safety certificate? The installation notice goes to the grid operator before the work and reports what will be built. The safety certificate goes to it after the final inspection and proves that it was built safely. One does not replace the other — and the certificate may be dispensed with only for work that is not reportable either.
Sources: Low-Voltage Installation Ordinance (NIV, SR 734.27), Art. 23, 24, 25, 38 and 42, as of 31 October 2025, fedlex.admin.ch. Federal Inspectorate for Heavy Current Installations ESTI, Directive No. 221 «Meldepflichten bei allgemeinen und eingeschränkten Installationsbewilligungen» (reporting duties for general and limited installation permits), version 0621, valid from 1 July 2021. ESTI, FAQ «Periodische Kontrollen, Sicherheitsnachweise» (periodic inspections, safety certificates), as of 22 July 2021, esti.admin.ch. This article is not legal advice; in case of doubt, the responsible grid operator or the ESTI decides.
We look at a real week from your business — 45 minutes, at your place or on screen.